Feasibility Study
PROJECT LOCATION |
PROJECT TYPE |
ESTIMATED VOLUMES PER YEAR |
East Africa |
Small Scale Bulk |
4 Mill MMBTU |
The Gas supply is in support of a 50MW power project in East Africa. The Electricity Project will require 3.5Mill MMBTU of natural gas in year one with a growth rate as follows as power consumption for the area increases at a minimum growth rate of 5.6% per year:
The project feasibility confirms that Volco Power is able to source and provide the necessary Natural Gas for the delivery to the power plant, in the form of LNG for the life of the project of +/- 30 years.
LNG will be delivered via bulk vessels (+18,000m3 LNG capacity) with a shallow enough draft adequate to birth in the harbour.
LNG will then be directly transferred to on-land storage capable of storing over 27 days’ supply of Natural Gas to the Power Plant.